I think this is just computed for completed tasks
this is the experiment that was useful, but we stopped it, because. convergence has happened before. than we expected
we just started logging metrics in clearml
Does this only work for the completed status?
and does not take into account failed and ABORTED experiments?
I'll check the code - it's possible this is calculated for specific task types - what kind of tasks do you have there?
And why can it be that the displayed time is zero?
although the experiments were considered for several days
Hi CheerfulGorilla72 , this is calculated by summing up the reported run time for all the tasks in the project